Rust treatment on pithead gear.

JENOSEEL

 

Rust treatment and rust prevention on electrical equipment.
Home.Applications.Information.How to use.Product range.Jenolite.FAQ s.Ordering.Contact us.Index.

Jenoseel Primer -  Application

The above information is based on tests and on site experience and may vary depending on site circumstances. If in doubt, apply small test area.

Application

 

1. Prepare surface as specified. Surface to be protected must be clean, dry, sound and free of any contamination.

 

2. Stir contents of can VERY thoroughly.

 

3. Brush apply at a wet film thickness of 78 microns, giving a dry film thickness of 35 microns. Leave 10-15 minutes to dry (in good airflow) and then apply second coat.

For maximum protection, ALWAYS brush apply TWO coats of Jenoseel Primer, allowing 10/15 minutes minimum*, 1 hour MAXIMUM* between coats.

 

 

Notes

1. * Drying times at 20ºC and with good airflow. Poor ventilation will greatly extend drying/overcoating times.

 

2. # Theoretical figure. Typical coverage 8-10m2/litre depending on substrate, method of application etc.

 

3.  A second primer coat is recommended to ensure adequate cover over rust peaks. Allow 10/15 minutes minimum, 1 hour MAXIMUM between primer coats.

 

4. Overcoating times

Between coats Jenoseel Primer -  12/15 minutes minimum, 1 hour maximum (in good airflow).

Over Jenoseel Primer - leave overnight (No maximum, although surface may need cleaning or repairing if left for extended period).

 

Specification  

 

Coverage (m2/litre):   13 (theoretical) #

 

Flash Point:   24ºC

 

Film thickness wet:   78 microns

 

Film thickness dry:   35 microns

 

Volume solids:    45%

 

Overcoat (after Jenoseel):   see below.  

 

Equipment cleaner:  No.  4 Solvent